COVID Holds Up New College Residence
Tuesday September 29th, 2020, 9:00am
Hello time traveller!!
This article is 1513 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
COVID-19 had delayed the opening of the new student residence at St. Clair College.
Ground was broken on February 28th and the site was shut down a few weeks later due to the pandemic.
Construction resumed later in the summer and foundations have been completed as well as site services.
Installation of the new modular units is slated to start at the end of November 2020 with an expected completion by the end of January 2021.
Substantial completion of the project is slated for July 16th, 2021. This will give the management company approximately one month to set up all requirements for a fall 2021 opening.