Construction is continuing along the Windsor-Essex Parkway, with construction crews working on building tunnels and bridges throughout the project corridor. Pile driving activities on nine of the Parkway structures is complete. Pile driving continues at the Oakwood Tunnel that began in early November and will take approximately two months to complete. Later this week/early next week, the pile driver from the Oliver Estates Tunnel will move to the Hearthwood Tunnel and a third pile driver will be operating at the Grand Marais Tunnel.