Weekly Windsor Construction Update
Friday May 3rd, 2013, 3:00pm
Hello time traveller!!
This article is 4020 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
Wyandotte Street West:
Intersection of Wyandotte and Campbelle closed for street scape improvements until June 8th.
Sydney Avenue:
Sydney Avenue will be closed between Walker Road and Riberdy Road for road paving and construction of the Sydney/Walker intersection until June 3rd.
Wyandotte Street East:
Watermain Reconstruction between Glidden and St. Rose until August 31st.
Byng Road:
Watermain Reconstruction between Ypres and Memorial. Memorial Drive will be closed between Ida and Turner until August 31st.
Provincial / Cabana Intersection:
Provincial Road and Cabana Road East will be reduced to one lane of traffic in each direction through the construction zone on a temporary basis for the concrete sidewalk construction and landscaping work for two more weeks.
Walker Road:
Road Reconstruction is taking place on Walker Road From E.C. Row Expressway to Foster Avenue until the end of June. Lane restrictions are in place.
Isack Drive:
Closed between Wyandotte Street East and Cedarview Street for watermain reconstruction until the end of May.
Pelissier Street:
Closed between Giles Boulevard West and Jackson Street for watermain reconstruction until the end of June.