Huron Line Construction Almost Complete
Wednesday June 19th, 2019, 7:20pm
Hello time traveller!!
This article is 2028 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
Work is almost complete on the 5.5-million dollar reconstruction project on Huron Church Road between Malden Road and Dorchester Road.
Starting later this week, phase three will get under way, which will see two-way traffic split, with southbound traffic diverted to a single southbound lane and northbound traffic remaining where it currently is in a single northbound lane.
Once the transfer of traffic is complete, reconstruction work will commence on the median portion of the roadway. That work is expected to take about a week and a half.
The reconstruction project is scheduled to be complete by July 5th, 2019.