Essex County Highway Construction This Week

Sunday June 7th, 2015, 5:00pm

0
0

Hello time traveller!!
This article is 3434 days old.
The information listed below is likely outdated and has been preserved for archival purposes.

County Road 22:
At the intersection of County Road 2 (at the Puce Recreation Center) will have lane restrictions until September 4th.

County Road 2:
At the intersection of County Road 22 (Puce Recreation Center) will be open only in the northbound direction until September 4th.

County Road 2:

Will be closed at Big Creek (east of County Road 39) for bridge rehabilitation until August 2015.

County Road 11:
Will be closed at Sucker Creek (McGregor Area) for bridge rehabilitation until June 11th.

County Road 2:

Will be closed at Big Creek (Lighthouse Cove area) for bridge rehabilitation until Mid August, 2015.

County Road 7:
Will be closed at Highway 3 from June 10th at 1am to June 13 at 5am for the installation of a pedestrian bridge for Herb Gray Parkway Construction.

Road Painting Operations:

Line painting on County Roads will occur throughout the warmer months. The operations are clearly identified with truck mounted signs. To avoid driving in the “wet paint” do not attempt to pass these slow moving trucks.

windsoriteDOTca
Daily Newsletter

Sign up to receive all the latest, local news stories you may have missed!

We don’t spam! Read our privacy policy for more info.

Do You Like This Article?

Content Continues Below Local Sponsor Message
Content Continues Below Local Sponsor Message
Content Continues Below Local Sponsor Message