Border Road: Pile Driving for Bridge 10 Ends
Wednesday May 23rd, 2012, 10:15am
Hello time traveller!!
This article is 4528 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
Pile driving for the south abutments of Bridge 10 and part of the Hearthwood Tunnel (T-10B) are now complete.
The pile driver from Bridge 10 has been moved to the south abutments of Bridge 9 (between Cabana Road and Geraedts Drive) and work began late last week.
The pile driver from T-10B is being moved to the south abutments of Bridge 11 (west of Howard Avenue) and work is expected to begin late this week.