Road Construction You Should Know About This Week
Sunday July 24th, 2016, 4:00pm
Hello time traveller!!
This article is 3055 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
Here is a look at road construction projects in the City of Windsor this week. Each Sunday we will provide an updated list of the current projects underway and their expected completion dates.
Howard Avenue:
Will be restricted to one lane in each direction from south of Hyde Street to ETR tracks, for road resurfacing until August 8th.
Montreuil Avenue:
Will be closed from Riverside Drive East to dead end, for road reconstruction until August 15th.
Ironwood Drive and Sprucewood Avenue:
Will be closed between Maplewood Drive and Cherry Blossom Drive and Sprucewood Avenue will be closed between Cherry Blossom Drive and Ojibway Parkway for sewer rehabilitation until August 18th.
Lillian Avenue:
Will be closed from north of Ottawa Street to South of Erie Street East for road work until September 9th.
Randolph Avenue:
Will be closed from Tecumseh Road West to Algonquin for road reconstruction until August 31st.
St. John Street:
From Clairview Street to Menard Street will experience traffic restrictions for sewer, water main and road reconstruction until October 31st.
Victoria Avenue:
Will be closed from Wyandotte Street West to Erie Street West for water main construction until August 28th.
E.C. Row Expressway:
Lane restrictions will take place in the westbound lanes between Central Avenue and Walker Road as part of the bridge repair project at the CNR and Walker Road structures until October 28th.
Marentette, Vimy and Lens Avenues:
Will have traffic restrictions in place for sewer, watermain and road rehabilitation until December 16th.
Villaire Avenue and Edgar Street:
Will have traffic restrictions in place for boulevard restoration until July 31st.
Wyandotte Street East:
Will be closed from Strabane Avenue to Cadillac Street for water main construction until August 26th.
Belleview Avenue:
Will be closed for water main construction from Wyandotte Street East to Riverside Drive East until August 26th.
Windsor Avenue:
Will be closed between Wyandotte Street and Erie Street for road and water main construction until July 29th.
Mercer Street:
From Erie Street East to Giles Boulevard East will be closed for water main construction until July 29th.
Moy Avenue:
From Wyandotte Street East to Giles Boulevard East will be closed for water main construction until July 29th.
Queen Street:
From Prince Road to South Street and Watkins Street from Queen Street to King Street will be under construction for sewer relining and road rehabilitation until August 5th.