Road Construction You Should Know About This Week
Sunday August 31st, 2014, 4:00pm
Hello time traveller!!
This article is 3781 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
On Going:
Homedale Boulevard:
Will be closed from Wyandotte Street East to Raymond Avenue for asphalt resurfacing until September 12th.
Aubin Road:
Will be closed from Tecumseh Road East to Guy Street for asphalt resurfacing until August 29th.
Carling Crescent:
Will be closed from Isack Drive to Cedarview Street for asphalt resurfacing until September 5th.
Christopher Drive:
Will be closed from Alan Crescent to Carling Crescent for asphalt resurfacing until September 5th.
Alan Crescent:
Will be closed from Isack Drive to Christopher Drive for asphalt resurfacing until September 5th.
Matthew Brady Boulevard:
Will be closed from Wyandotte Street East to St. Rose Avenue for asphalt resurfacing until September 12th.
Watson Avenue:
Will be closed from Cedarview Street to Clairview Avenue for asphalt resurfacing until September 12th.
Norman Road:
Will be closed from Adstoll Avenue to Joinville Avenue for road reconstruction until November 15th.
Cadillac Street:
Will be closed from Alice Street to north of Reginald Street for sewer, watermain and road rehabilitation until December 4th.
Reginald Street:
Will be closed from Cadillac Street to Drouillard Road for sewer, watermain and road rehabilitation until December 4th.
Hickory Road:
Will be closed from Metcalfe Street to Seminole Street for sewer, watermain and road rehabilitation until December 4th.
South Cameron Boulevard:
Will be closed for road reconstruction from Dougall Avenue to Northwood Street for road reconstruction until September 15th.
Cedarview Street:
Will be closed from Isack Drive to Riverside Drive East for road rehabilitation until September 12th.
Wyandotte Street East:
Will have lane restrictions (one lane in each direction) from Langlois Avenue to Windsor Avenue for watermain construction until September 15th.
Wyandotte Street East:
Will be closed from Gladstone Avenue to Argyle Road for watermain and road construction until September 30th.
Pelissier Street:
Will be closed between Wyandotte Street West and Giles Boulevard West for road and water main construction until October 31st.
Roselawn Drive:
Will be closed from Woodland Avenue to Longfellow Avenue for watermain construction until September 12th.
Northwood Street:
From South Cameron Boulevard to Dandurand Avenue, will be closed for watermain construction until September 5th.
California Avenue:
From Wyandotte Street to University Avenue will be closed for sewer, watermain and road reconstruction until August 31st.
E.C. Row Expressway:
Lane restrictions will take place on the E.C. Row Expressway at the CASO Bridge between Dougall Avenue and Howard Avenue for bridge rehabilitation until September 19th.
St. Rose Avenue:
Will be closed from Lauzon Road to Virginia Avenue for sewer, watermain and road reconstruction until September 1st.
Intersection of Ojibway Parkway and Broadway Boulevard (west of Ojibway Parkway):
Will be closed for Parkway construction until October.