Huron Church Construction Starting In April
Tuesday March 23rd, 2021, 10:54am
Hello time traveller!!
This article is 1350 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
Work is about to get underway on the next phase of Huron Church construction between Tecumseh Road and College Avenue.
The work includes:
- New concrete pavement.
- Concrete curbs, medians and sidewalks between Girardot Street and College Avenue.
- Replacement of select water mains and services.
- Street lighting improvements.
- New traffic signal infrastructure at the intersection of Huron Church and Tecumseh.
Stage 1 of construction will see the complete closure of the roadway’s southbound lanes, shifting all traffic to the northbound lanes where two-way traffic will be temporarily installed.
Once Stage 1 is complete, traffic will shift to the north side. Two southbound lanes and one northbound lane of travel will remain available on Huron Church throughout construction. During construction, no left turns will be permitted off Huron Church Road through the construction zone.
The $4.9-million reconstruction project is funded by $3 million from the provincial government under the Connecting Links Program. The City will contribute the remaining funds.
Work starts mid-April and, weather permitting, is expected to be complete by September 2021.