Road Construction You Should Know About This Week
Sunday September 27th, 2015, 4:00pm
Hello time traveller!!
This article is 3389 days old.
The information listed below is likely outdated and has been preserved for archival purposes.
Here is a look at new and on going road construction work in the City of Windsor. Updates are posted each Sunday afternoon.
Ontario Street:
Will be closed from Pillette Road to Raymo Road for storm, sewer and pavement rehabilitation until October 30th.
Villaire Avenue:
from Raymond Avenue to the CNR tracks- south of Edgar Street will be closed for sewer, watermain and road construction until December 31st.
Rossini Boulevard:
Will be closed from Seminole Street north to the CN Tracks for storm, sanitary sewers, watermain and repaving until December 1st.
Metcalfe Street:
will be closed from the alley west of Rossini to alley east of Rossini for road repaving until December 1st.
Watkins Street:
From King Street to Bloomfield Road will be under construction for sewer, watermain and road rehabilitation until November 15th.
King Street:
Will be under construction from Prince Road to South Street for sewer, watermain and road rehabilitation until November 15th.
Jos St. Louis Avenue:
Will be closed between Rose Street south to the cul-de-sac for sewer, road and watermain reconstruction until December 15th.
McDougall Street:
From Logan Street to the ETR Railway will be closed for construction of watermain, sanitary sewers and storm sewers until October 9th.
Wyandotte Street East:
Will be reduced to one lane in each direction between George Avenue and Pillette Road for watermain and road construction until October 30th.
Wyandotte Street West:
Will experience lane restrictions from Caron Avenue to Ouellette Avenue for watermain construction until October 9th.
Pillette Road:
Will be restricted to local traffic only, from north of Tecumseh Road East to south side of Seminole Street, for watermain construction until October 30th.
Edward Avenue:
Will be closed from Wyandotte Street East to Edgar Street for sewer, watermain and road rehabilitation until October 2nd.
Fairview Avenue:
Will be closed from Edgar Street to St. Rose Avenue for construction of watermain, sanitary and storm sewers until October 2nd.
Caroline Street:
Will be closed from Dougall Avenue to Bruce Avenue for road reconstruction until October 2nd.