free web stats
ClearThu
21 °C
70 °F
Mostly SunnyFri
23 °C
73 °F
ClearSat
28 °C
82 °F
ClearNow
16 °C
61 °F
Thursday May 17th, 2012

Border Road: Highway 3 Road Diversion Opens to Traffic

Flickr Video After months of design, preparation and paving, the Windsor-Essex Parkway’s first diversion road has opened to traffic. Westbound traffic traveling after St. Clair College will be presented with a near seamless transition as the road bends to the right through an area previously occupied by...MORE

Thursday May 10th, 2012

Border Road: Trillium Court Community Replacement Homes Completed

Construction is into its final stages of the relocation of Trillium Court, a public housing area in LaSalle that has to be demolished to make room for the W-E Parkway. Finishing touches such as landscaping and driveway paving are underway. An entirely new...MORE

Wednesday May 9th, 2012

Border Road: Pile Driving Starts for Tunnel 10B

Pile driving operations — known for their noise — continue on the W-E Parkway route this week. A pile driver is working to bury steel piles into bedrock to support “Tunnel 10B″ at the side of Highway 3 near Windsor Crossings. Tunnel 10B will be utilized by...MORE

Tuesday May 8th, 2012

Border Road: Highway 3 Diversion Paved

W-E Parkway construction crews have began paving portions of several ‘diversion’ routes along existing Highway 3 and where Highway 3 becomes Huron Church. The existing route will switchover to diversions sometime in June so portions of the old road can be reconstructed into the new W-E...MORE

Sunday April 29th, 2012

Update: North Talbot Overpass Rebuild Nearing Completion

North Talbot overpass nearing completion The 401 was closed for a 24 hour period, starting on Saturday April 28th at 1am (Eastbound 401 between Highway 3 and Provincial and Westbound 401 between Manning and Highway 3) to allow for a rebuild of the expanded North Talbot...MORE

Thursday April 26th, 2012

Border Road: Highway 401 Closes this Weekend for North Talbot Bridge Construction

Highway 401 will be closed between Highway 3 and Manning Road this weekend. The closure is necessary for construction crews to begin rebuilding the North Talbot Bridge which was demolished last year. The 401 will close starting on Saturday April 28th at 1am (Eastbound 401 between Highway...MORE

Wednesday April 25th, 2012

Border Road: Pile Driving Begins on WE-Parkway

Noisy pile driving operations on the W-E Parkway route have begun. A pile driver is working to bury steel piles into bedrock to support “Bridge B-10″ at the side of Highway 3. Bridge B-10 will carry Highway 3 traffic over the new Windsor-Essex Parkway. The bridge will...MORE

Tuesday April 24th, 2012

Border Road: Grand Marais Drain Culvert Built, Ready for Diversion Road

Workers from Facca Construction have finished building a “three-cell box-culvert” to support the Parkway’s new service road and Huron Church Diversion over the Grand Marais Drain. Construction of the all-concrete structure started in the Winter and a roadway to be built above it will connect two...MORE